Under Our Feet the Whole Time: Nevis Is Finally About to Drill for Its Own Power

Nevis Peak wrapped in cloud, with a roadside food shack in the foregroundNevis Peak shrouded in cloud behind a roadside food shack, near the Hamilton Estate geothermal site

There’s a version of this story that’s been “almost happening” for most of the last decade. Exploratory drilling confirmed real geothermal heat under Nevis back in 2018 — water hot enough, deep enough, to run a power plant. Then came financing gaps, delays, more delays, the kind of long quiet that makes people stop believing a project is real. That quiet is ending.

In late August, a NEVLEC delegation flew to Iceland to put eyes on the actual drilling rig before it ships here — a 272-metric-tonne machine the project has nicknamed “Tyr.” UK-based Scotia Drilling Consultants ran it through a full technical inspection: structural, mechanical, safety, the works. Premier Mark Brantley’s read on the moment was blunt: “Once this drill rig inspection is completed, then it would mean that we have now done all that is necessary in order to move this to the next phase.” As of the start of September, the government was saying drilling should start within 60 days of that inspection — which puts the real, ground-breaking start of this project somewhere in the weeks right around now.

Here’s what’s actually planned at the Hamilton site: a handful of wells (reports vary between five and six — three or so for production, the rest for reinjecting water back underground), drilled by Iceland Drilling under a contract won through competitive tender, with Iceland-based firm COWI building the well pads. The target is a 30-megawatt geothermal plant — more electricity than St. Kitts and Nevis together currently use. One report called the resource under Nevis one of the best in the world; we haven’t been able to independently confirm that specific ranking, so take it as a strong claim worth watching rather than a settled fact.

Why this matters more than a typical infrastructure story: right now, St. Kitts and Nevis runs almost entirely on imported diesel, which means every power bill on the island is quietly tied to global oil prices and shipping costs nobody here controls. Geothermal flips that. It’s heat that’s already here, that nobody can cut off, that doesn’t arrive on a tanker. The federation has set a goal of 100% renewable power by 2030, and this project — more than solar panels on a few roofs — is the piece that could actually get there, with talk of an undersea cable eventually sharing Nevis’s power with St. Kitts.

There’s a bigger thread here too, one we touched on last week writing about the pressure closing in on citizenship-by-investment revenue: Premier Brantley has been saying for a while that geothermal is a real part of what replaces that money if CBI funding keeps shrinking. A power plant that could someday export electricity to neighbors isn’t just a utility upgrade — it’s the beginning of an answer to “what does Nevis’s economy look like if the passport business goes away.” Delegations from Saint Martin have already come by to talk clean-energy cooperation, with similar conversations happening with Antigua and Barbuda. That’s Nevis being looked at as a regional energy supplier, not just a place trying to keep its own lights on.

None of this is finished. The drilling phase alone is expected to run well over a year, with dozens of workers — local and imported — based at the site the whole time. The payoff in actual lower power bills is realistically still a couple of years out. But after a false start in 2017 (that attempt got knocked sideways by Hurricanes Irma and Maria), years of financing limbo, and a government that’s already put roughly US$6 million of its own money into getting this far, the gap between “we’re planning this” and “the drill is in the ground” is about to close. That’s worth marking.

A note on what’s unverified: the exact well count (five vs. six, depending on the source) and the “one of the world’s best” resource-quality claim haven’t been confirmed against a primary technical report — treat those specifics as provisional until NEVLEC or the geothermal project team publishes firmer numbers.

Sources

  • NEVLEC delegation advances geothermal preparations — Energy Global
  • Nevis delegation inspects rig prior to mobilization for geothermal drilling — ThinkGeoEnergy
  • Drilling operations for Nevis Geothermal Project to kick off within 60 days — WINN FM
  • Nevis selects Iceland Drilling for geothermal drilling operations to commence in 2026 — ThinkGeoEnergy
  • Nevis Geothermal Drilling To Begin Later This Year — ZIZ Online